The Executive Engineer being the executive had is responsible to the Superintending Engineer for the preparation of realistic estimates, effective execution and management of all the works and establishment. In order to enable the Executive Engineer to discharge his duties diligently, Asst. Engineers & Junior Engineers assist him as field functionaries.
i) River Embankment:
A total length of 83.25 km. of river embankment of different river, like Subarnarekha, Jambhira, Budhabalanga, Gangahar, Sono and Baitarani are maintained by the Division under M/R grant.
ii) Activities on Panipanchayat:
Activities and Progress on Panipanchayat of the Medium Irrigation Projects under this Division are given in ANNEXURE- II. The Project committee has been formed in Balidiha, Kalo & Sunei Irrigation Project. Fresh election will be conducted as most of the PPs have completed their tenure.
iii) Flood damaged repair works:
Flood damage report has been submitted occurred during September 2019. The work will be taken after receipts of funds.
iv) O.H. AWMIP (A.D.B. Assistance):
There is no A.D.B. Assistance work taken under this Division.
v) N.R.E.G.A:
Total 116 nos of works has been approved under MGNREGA for Rs. 423.00 lakhs during the year 2019-20. 61 nos of works have been taken up with an expenditure of Rs. 113.82 lakhs.
6) Duties to be Prepared to Achieve the Mission:
The duties assigned to achieve the mission includes preparation/ Sanction of realistic estimates, floating of tenders, drawal of Agreements for effective execution of repair and maintenance works of three medium irrigation projects, and the river embankments (TRE). In addition formation of new Panipanchayats and to conduct Participatory Walk Through (PWT) for the maintenance of some of these projects where canal systems are handed over to Panipanchayats to take up the works out of grants-in-aid. In addition the flood management, creation of irrigation potentials and collection of water rate from the industrial units are also part and parcel of the assigned duties.
7) Details Of Services Rendered:
Repair and maintenance of the canal systems of all these three medium irrn. Projects so as to make them irrigation worthy and efficient flood management and repair maintenance of river embankments (TREs) so as to protect the lives & properties of the inhabitants of the adjacent villages are some of the illustrative services rendered by this Division.
[ : Information available in this manual was last accses on 08/05/2026 ]
While all efforts have been made to make this website as authentic as possible, I & PR deptt. and Luminous Infoways will not be responsible for authentication of proactive disclosure and annual report. Respective department and Public Authority is responsible for their information. Users are advised to verify/check any information with the relevant department(s) and/or other source(s), before acting on the information provided in the Portal.